Progress Reports:
Feb . 6,2003
Feb. 12,2003
April. 2003

Please note:
This is an informational website, provided by the Engineering Firm,
Kerr Wood Leidal Associates Ltd., and the contractor, PW Trenchless Construction. Although we strive for accuracy, this is a project very much under constructions with updates when needed to inform residents of the area of any information that comes up. Please check back regularly for more information. Last updated February 12, 2003
Prior to Feb 6, 2003 all work on site was in preparation for the pipe bursting that started the week of Feb. 3, 2003.
Up to this point six burst have taken place out of the possible 13 in Phase one.

Page two of Feb. 6, progress report


    [Next] [Last]


[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
Using a Ditch Witch Subsite Electronic locator one of the workers locates buried utilities Using a "fish tape" inserted up the pipe, a small electric current is applied to the "fish tape" to aid location of the sanitary sewer Preparation of the entrance hole Working around the existing services, this is the finished connection.
[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
burst005
300 X 353
17 KB
burst007
420 X 315
26 KB
burst008
500 X 171
14 KB
burst009
450 X 262
19 KB
[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
[Click to enlarge image]
burst013
450 X 298
18 KB
burst011
450 X 151
18 KB
burst012
400 X 300
19 KB
burst014
330 X 384
24 KB


    [Next] [Last]

The webmaster

| Home | Photos |