The City of West Vancouver.

Twenty-second Street, just up from Marine drive, approximately 280m of sewer is replaced via pipebursting. The job is broken into 3 bursts. Traffic is re-routed during the bursts.

The exit pit with the winch in place during the burst Near the end of the burst the tail end of the pipe is raised of the ground. One of the workers is adjusting the airhose. PW Trenchless has aquired this larger truck for hauling around the 14" tool and all it The entrance pit. On the left side of the photo the sewer by-pass pipes can be seen.
The entrance pit with the manhole "window" visible. Looking down into the manhole during the burst, as the new HDPE pipe goes right through it. The sewer by-pass system set up upstream of the burst