![]() |
||||||
| Progress Report Nov. 5 Pipeburst Oct. 28 Pipeburst Oct. 17 Pipeburst Oct. 10 Preparations |
Please note: This is an informational web site, provided by the Engineering Firm, UMA Engineering Ltd., and the contractor, PW Trenchless Construction. Although we strive for accuracy, this is a project very much under constructions with updates when needed to inform residents of the area of any information that comes up. Please check back regularly for more information. |
|||||||||||
![]() |
Section 2, from 9393 Kingsley Cr. to 9417 Kingsley Cr. was completed October 28, 2002. Unlike the first burst it was not over in 30 minutes. This burst was over 100 m long but took a couple of hours to complete. There were no complications, but possibly wetter ground conditions contributed to the longer time needed. | |||||||||||
![]() |
||||||||||||
|
Click on the thumbnails below to get a larger version.
|
||||||||||||