2022 Port Moody Sept 12 Inverted CIPP Liner

2022 PortMoody September 12

On September 12 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed via air pressure. This is not a new experimental process and has been used for 5 decades and the life of 25,000 miles of pipe worldwide has been extended via the Insituform® CIPP.

The process had started months earlier with PW Trenchless Construction installing a sewer by-pass system to ensure the forcemain sewer main would be dry for the lining process and any flows of the sewer would be maintained while the process was proceeding. Entrance and exit pits were excavated and sored and fenced off to ensure the safety of the public on these well used trails. Although the first sewers to be relined were gravity mains, and the bypass system was not needed for the gravity lines, the lining process did not start till all the bypass system was in place, and all excavations completed.

The starting date for the Edmonton based Insituform crew, was a dry sunny day that had followed an unusually long dry period for the Lower mainland area of British Columbia. The crew showed up and the first process, was the obligatory wheel washing process to ensure no contamination into the parks eco-system. The Insituform crew did a camera inspection of the line, and they could send up a cleaning wand if needed.

 Once inspected, the truck which controls the lining system was put in place by the entry point at an existing manhole. At both the entry point manhole and the exit point manhole, a pipe testing plug was installed into the pipes entering the manhole that were not part of the lining process that day. This ensure no stray debris enter the “Host” pipe, the pipe that is to be lined.

The truck holding the liner is set up in place and the new liner has been “wetted” and needs to be kept cool with bags of ice surrounding the pipe supply. The liner is a Poly sleeve that has a felt inner membrane that is impregnated with a fiberglass type resin and pulled through a series of rollers at a specific height to ensure the whole membrane has an equal and proper amount of resin throughout the length of the liner.

A pipe liner inverter is set up over the entrance manhole and the liner is fed trough the inverter and the end is inverted, and held in place with steel bands. High pressure air is inverted into the plenum of the inverter to force the liner downwards into the entrance manhole and it is redirected by a wedge in the invert of the manhole that directs the liner towards the pipe to be lined.

As the air continues to be forced into the inverter, a liquid lubricant is applied to the “pipe Inverter” to allow the new liner to be installed with the minimum of friction and no damage to the liner. While the lubricant was added and poly tub was placed on the ground to make sure if any liquid dripped out it would be captured and not allowed to impregnate the ground of the park.

As the liner is inverted into the host pipe, the resin impregnated felt inner part of the liner inverted and is forced against the inside of the host pipe. It is not dragged along but rather is installed from the inside out and goes all the way to the exit manhole where it is guided out of the manhole via wood wedges that force it up and out of the manhole.

Once the liner was installed throughout the host pipe, a sleeve made of PVC pipe, the same diameter of the host pipe is placed around the excess liner on the ground out side of the exit manhole. This is marked with the date and batch number of both the liner material and the resin to provide a test sample of the liner.

The end of the installed liner is tied off and a small hole is drilled into the liner and a steel manifold pipe is inserted into the hole as a port to let the pressurised air escape. This steel pipe has a pressure guage along with a valve to allow the pressure to build up and keep a constant pressure to keep the liner mated closely with the host pipe. Once pressurized, steam is introduced to start the curing process. Temperature probes are carefully monitored to ensure critically important constant and even curing times and temperatures.

After a predetermined time, set by the length and diameters of the project, with a considerable safety margin, the steam is replaced by air and the pipe is cooled and then the pressure removed. The ends of the pipe are cut off and removed in sections to allow access to the manholes. After accessing the manholes the ends of the liners are carefully cut to correct shape of the host pipe as it enters the manhole.

Cleanup and removing of the excess is fast and careful, with all necessary means used to ensure no damage to the surrounding area or manholes.

Recent CIPP Projects

Fall 2022 Port Moody

2022 Port Moody Sept 28 On September 28 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed by pulling through the …

See Project

2022 Port Moody Sept 12 Inverted CIPP Liner

2022 PortMoody September 12 On September 12 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed via air pressure. This is …

See Project

Design - Build

An alternate tendering process where the contract is awarded to one entity which comprises both engineering and contracting.

Because PW Trenchless Construction offers such innovative solutions for underground utilities, it is often beneficial for the owner to request solutions based on a performance specification. This allows PW Trenchess to offer unique solutions while working with equally innovative engineering companies. Learn more about design - build here!

More Info

New Installation

New installation methodologies include HDD & traditional open cut Learn more about new installation here!

More Info

Pipe Replacement & Rehabilitation

In this day & age of pipe systems reaching the end of their projected lifespan, pipe replacement and pipe rehabilitation have become major fields of engineering.

PW Trenchless Construction provides viable options such as pipe bursting, loose fit lining and internal pipe re-construction whether partial & fully circumferential. Learn more about pipe replacement & rehabilitation here!

More Info

Culvert Rehabilitation

The aging culverts under roads and highways in many case have reached the end of their engineered life-span. We consider the rehabilitation or replacement of these culverts to be vital to our built environment.

PW Trenchless has been a pioneer in working with MOTH, railway companies and municipalities in developing rehabilitation methodologies for the hundreds of thousands of culverts that currently exist in BC. We have offered solutions in both procurement and construction from design-build to sliplining, invert rehabilitation and full circumferential relining. Learn more about culvert rehabilitation here!

More Info

Point Repairs

Often pipe failure can be concentrated to one section, for various reason, leaving the rest of the pipe in good condition. The repair of these localized failures are know as external point repairs (EPR's).

EPR's demonstrate PW's ability to work as both a trenchless and civil contractor, completing EPR contracts using our civil contracting skills and assisting other pure trenchless contractors who only have the capacity to work in an existing pipe. Learn more about point repairs here!

More Info

Pipe Upsizing

Pipe upsizing is the fundamental concept of pipe bursting.

The vast majority of pipes are less than or equal to 200mm in diameter, but with today's densification practices of urban design, there is a major demand to increase current capacity to handle extra flow. Pipe bursting provides the ideal solution to this issue, particularly in an urban setting. Learn more about pipe upsizing here!

More Info

Horizontal Directional Drilling

Horizontal Directional Drilling is a low impact Trenchless construction service where pipe is installed in a shallow arc along a bore path which has been created by a drilling rig. Often the terms Horizontal Directional Drilling (HDD) and Directional Boring are used interchangeably, but in our industry we use the word “boring” when we utilize smaller sized drilling rigs with small diameters for short crossings in the hundreds of feet, and we use the word “drilling” when we utilize larger rigs with large diameters for long crossings in the thousands of feet. Learn more about horizontal directional drilling here!

More Info

Primus Lining

Primus Line® is a flexible sliplining solution for the trenchless rehabilitation of pressure pipes. The system consists of a flexible Kevlar® reinforced liner and specially developed end fittings. Primus Line® is not bonded to the host pipe and is self-supporting. An annulus remains between Primus Line® and the host pipe.

Developed by experienced engineers, the system is suitable for different media as well as various application needs and has already proven itself in numerous projects.Learn more about primus lining here!

More Info

Interested? Let’s Talk

  • This field is for validation purposes and should be left unchanged.

Clients We Serve

City of New Westminster logo
City of Delta logo
City of Surrey logo
City of Port Coquitlam logo
UBC logo
City of Coquitlam logo
City of Nanaimo logo
City of Pitt Meadows logo
City of Vancouver logo
BC Rail logo
City of Burnaby logo
City of Whistler logo
City of Victoria logo
City of Metro Vancouver logo
City of Squamish logo
City of West Vancouver logo
City of Richmond logo
City of Abbotsford
City of Chilliwack
Township of Esquimalt
City of Maple Ridge
City of North Vancouver
City of Port Moody
Regional District of North Okanagan
Town of Sidney

Join Our Team

When you join PWT, you become part of a community of people who are engaged in the most innovative practices in the Trenchless Industry. We have been instrumental in setting up a scientific method for cities to gain carbon offsets/credits from their use of trenchless construction. This system has been reviewed by the BC Government and has been approved as of December 2018. We expect to see it in common use shortly.

Stay At The Forefront Of Trenchless Technology

Subscribe to our newsletter for cutting-edge industry updates, expert knowledge, and exclusive content.

  • By clicking subscribe, you agree to receive emails from PW Trenchless and accept our Privacy Policy.

  • This field is for validation purposes and should be left unchanged.
Let's Talk