Fall 2022 Port Moody

2022 Port Moody Sept 28

On September 28 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed by pulling through the existing, or “Host” pipe. The sanitary sections of the sewer are installed using the iPlus® Glass process. According to the Instituform website, the iPlus® Glass liner is reinforced with glass fiber and can be cured using an ultraviolet (UV) method. This trenchless CIPP solution is a jointless, seamless, pipe-within-a-pipe. It can be used to rehabilitate pipes ranging in diameter from 6 to 48 inches (150mm to 1200mm).

Unlike the CIPP method used on the sanitary gravity sewers in the park earlier in the month, there is quite a bit of preparation need to complete these projects. Along with the bypass pumps and piping installed for the sanitary forced sewers. Entrance and exit pits need to be excavated and shored with trench shoring cages. The sanitary sewer is a forced main and as such does not have open manholes to install liners through. The entrance and exit pits are paced at predetermined lengths of the pipe main, and are sensitive of the surrounding trees of the park.

The pits were all excavated and shored by the crews of PW Trenchless Construction during the months prior to the relining operations. The ends of the pipe to be lined are cut perfectly square on the day of the burst with a strong section of C-900 Waterman PVC pipe attached with a flexible coupling. This will allow for ratchet straps to hold the liner in place without fear of cracking the host pipe.

The iPlus® Glass installation process is much different than the Insituform® CIPP installation used on the Port Moody Gravity Sewer mains that PW and Instituform installed early on in September. While the camera is being sent up the host pipe for it’s initial inspection the morning of the lining, a plastic liner is attached to the camera rig and pulled back trough the host pipe, along with a pull rope for installing the tugger cable. This plastic liner aids in reducing friction when pulling the  liner through the host pipe and reduces the chance of damaging either.

To help keep the liner in place, a portion of the liner is sent up the other part of the Host pipe that will not be used that day, on the other side of the excavated pit. A sewer test plug is inserted and inflated and does a good job keeping the liner from slipping along with the liner as it is installed. The tugger cable is pulled through and attached to the liner, for pull back. A plywood deck is placed on an angle and the crate with the Liner is placed on top and the end of the liner is attached to the end of the cable and the liner is installed into the host pipe.

Once the liner is installed, at the far end, the “exit pit” where the tugger is located, a steel flange is attached and held in place with ratcheting straps. This allows for steam, air and the control cables utilized for the inflation and curing of the pipe liner to be inserted. At this point, where the liner was inserted, the “Entrance Pit”, the light apparatus is installed and a similar steel flange is inserted and held in place with ratcheting straps. Part of the plastic liner is also pulled over the end held in place with tape and straps. The lighting apparatus is installed in to the bag and the end is tied off. Air is inserted from the far end to inflate the liner and the clear plastic bag around the entrance pit end.

Once the liner is partial inflated, a slit is cut in the plastic and control and power cords are attached to the lighting apparatus. The lights are then placed inside the liner and the end is seal with a flange that allows for the control and power cords to go through the flange while the full pressure is applied. The lights are pulled all the way to the exit pit and the air pressure and heat are applied until the proper settings are reached. The lighting rig has numerous lights that cure the fiberglass resin impregnated liner until it is as durable as PVC pipe.

After a number of hours, almost 6 hours for the September 28, 2022 lining job, the pipe is fully set up and ready to be used. The project in the Port Moody Old Orchard park had a number of sections in a row  to be lined. Over the next few weeks, all the liners were installed, and uncharacteristically for the lower mainland area, the job was completed prior to the rains starting to fall.

Recent CIPP Projects

Fall 2022 Port Moody

2022 Port Moody Sept 28 On September 28 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed by pulling through the …

See Project

2022 Port Moody Sept 12 Inverted CIPP Liner

2022 PortMoody September 12 On September 12 , 2022, Insituform started to line the existing sanitary sewer lines that go through the Old Orchard Park. Insituform® CIPP is a cured in place pipe liner that is installed via air pressure. This is …

See Project

Design - Build

An alternate tendering process where the contract is awarded to one entity which comprises both engineering and contracting.

Because PW Trenchless Construction offers such innovative solutions for underground utilities, it is often beneficial for the owner to request solutions based on a performance specification. This allows PW Trenchess to offer unique solutions while working with equally innovative engineering companies. Learn more about design - build here!

More Info

New Installation

New installation methodologies include HDD & traditional open cut Learn more about new installation here!

More Info

Pipe Replacement & Rehabilitation

In this day & age of pipe systems reaching the end of their projected lifespan, pipe replacement and pipe rehabilitation have become major fields of engineering.

PW Trenchless Construction provides viable options such as pipe bursting, loose fit lining and internal pipe re-construction whether partial & fully circumferential. Learn more about pipe replacement & rehabilitation here!

More Info

Culvert Rehabilitation

The aging culverts under roads and highways in many case have reached the end of their engineered life-span. We consider the rehabilitation or replacement of these culverts to be vital to our built environment.

PW Trenchless has been a pioneer in working with MOTH, railway companies and municipalities in developing rehabilitation methodologies for the hundreds of thousands of culverts that currently exist in BC. We have offered solutions in both procurement and construction from design-build to sliplining, invert rehabilitation and full circumferential relining. Learn more about culvert rehabilitation here!

More Info

Point Repairs

Often pipe failure can be concentrated to one section, for various reason, leaving the rest of the pipe in good condition. The repair of these localized failures are know as external point repairs (EPR's).

EPR's demonstrate PW's ability to work as both a trenchless and civil contractor, completing EPR contracts using our civil contracting skills and assisting other pure trenchless contractors who only have the capacity to work in an existing pipe. Learn more about point repairs here!

More Info

Pipe Upsizing

Pipe upsizing is the fundamental concept of pipe bursting.

The vast majority of pipes are less than or equal to 200mm in diameter, but with today's densification practices of urban design, there is a major demand to increase current capacity to handle extra flow. Pipe bursting provides the ideal solution to this issue, particularly in an urban setting. Learn more about pipe upsizing here!

More Info

Horizontal Directional Drilling

Horizontal Directional Drilling is a low impact Trenchless construction service where pipe is installed in a shallow arc along a bore path which has been created by a drilling rig. Often the terms Horizontal Directional Drilling (HDD) and Directional Boring are used interchangeably, but in our industry we use the word “boring” when we utilize smaller sized drilling rigs with small diameters for short crossings in the hundreds of feet, and we use the word “drilling” when we utilize larger rigs with large diameters for long crossings in the thousands of feet. Learn more about horizontal directional drilling here!

More Info

Primus Lining

Primus Line® is a flexible sliplining solution for the trenchless rehabilitation of pressure pipes. The system consists of a flexible Kevlar® reinforced liner and specially developed end fittings. Primus Line® is not bonded to the host pipe and is self-supporting. An annulus remains between Primus Line® and the host pipe.

Developed by experienced engineers, the system is suitable for different media as well as various application needs and has already proven itself in numerous projects.Learn more about primus lining here!

More Info

Interested? Let’s Talk

  • This field is for validation purposes and should be left unchanged.

Clients We Serve

City of New Westminster logo
City of Delta logo
City of Surrey logo
City of Port Coquitlam logo
UBC logo
City of Coquitlam logo
City of Nanaimo logo
City of Pitt Meadows logo
City of Vancouver logo
BC Rail logo
City of Burnaby logo
City of Whistler logo
City of Victoria logo
City of Metro Vancouver logo
City of Squamish logo
City of West Vancouver logo
City of Richmond logo
City of Abbotsford
City of Chilliwack
Township of Esquimalt
City of Maple Ridge
City of North Vancouver
City of Port Moody
Regional District of North Okanagan
Town of Sidney

Join Our Team

When you join PWT, you become part of a community of people who are engaged in the most innovative practices in the Trenchless Industry. We have been instrumental in setting up a scientific method for cities to gain carbon offsets/credits from their use of trenchless construction. This system has been reviewed by the BC Government and has been approved as of December 2018. We expect to see it in common use shortly.

Stay At The Forefront Of Trenchless Technology

Subscribe to our newsletter for cutting-edge industry updates, expert knowledge, and exclusive content.

  • By clicking subscribe, you agree to receive emails from PW Trenchless and accept our Privacy Policy.

  • This field is for validation purposes and should be left unchanged.
Let's Talk