2022 Richmond Burkeville

The City of Richmond has commenced a 5-10 year project to replace and improve the water mains, sewers and roadways in the Burkeville area of Richmond near the Vancouver International Airport. This area has been prone to flooding so a newly expanded drainage system over and above the existing open ditches is needed to reduce the flood risk in the future.

Phase 1 and 2 have been completed and in Phase 3, along with PW Trenchless Pipe Bursting, all water mains will be replaced, trees and hedge trimmed or removed, installation of a new drainage system, and repaving of the road and installing a new gravel shoulder to roadways.

  From September 6th 2022 to October 28, 2022 PW Trenchless replaced 265m of existing sanitary mains via pipe bursting and was lucky to be able to do the work at the tail end of an extremely dry period of weather for the Lower Mainland. The water table is typically extremely high during normal times in Richmond, so the dry weather was a plus for this project.

The Burkeville area of Richmond is one area of Richmond that still has ditches, and when the crew was initially looking at the project in the Spring, the ditches were full of water.

The City had installed a sign for the residents to see the scope of the project and PW Trenchless’ part of phase 3 included:

-Clearing and tree removal at entrance and exit pits locations.
-Trimming trees that may interfere with excavation and mobilization.
-Excavations of entrance and exit pits.
-The dewatering of excavations if required along with the treatment of discharge water.
-Fusing of HDPE pipe on site within approved laydown area.
-Trenchless pipe bursting of 130m of existing 200mm (8″)AC pipes with 200mm HDPE.
-Trenchless pipe bursting of 130m of existing 250mm (10″)AC pipes with 250mm HDPE.
-Restoration of excavated areas.


On September 13th of 2022, after the long dry spell mentioned above, PW Trenchless Construction did two of the 6 bursts that are part of this project. The entrance and exit pits had been dug prior to the day of the burst, and the depth was not too deep. The pits were dry enough to just need a couple of smaller pumps to handle the ground water and De-watering was not needed. A rare occurrence for Richmond.

The tugging apparatus was installed and the pulling rods were inserted through two runs of pipe. Starting at 11a.m. And arrived in the entrance pit an hour later. The rods went right through one of the existing manholes near mid point of the two runs.

The first section of HDPE pipe had been staged in a park area near the burst and the road needed to be temporarily closed to traffic. Traffic for the area is extremely light as there are not very many homes and they were able to drive the other direction to access the subdivision.

Once the pipe was staged, it already had the pulling head attached, it was connected to the pulling rods and the burst commenced at 12:24pm and was finished at 12:52p.m.

The head was removed and the new section of pipe was staged alongside the roadway and the bursting head was attached. A bit of Hydro excavation was done around the gas main for safety and the second burst started at 2:20pm and finished at 2:37p.m.  The head was removed and the two sections of pipe were connected to the existing pipe at one end and grouted into the manholes where needed.

 

Recent Microtunneling Projects

2022 Richmond Burkeville

The City of Richmond has commenced a 5-10 year project to replace and improve the water mains, sewers and roadways in the Burkeville area of Richmond near the Vancouver International Airport. This area has been prone to flooding so a …

See Project

Design - Build

An alternate tendering process where the contract is awarded to one entity which comprises both engineering and contracting.

Because PW Trenchless Construction offers such innovative solutions for underground utilities, it is often beneficial for the owner to request solutions based on a performance specification. This allows PW Trenchess to offer unique solutions while working with equally innovative engineering companies. Learn more about design - build here!

More Info

New Installation

New installation methodologies include HDD & traditional open cut Learn more about new installation here!

More Info

Pipe Replacement & Rehabilitation

In this day & age of pipe systems reaching the end of their projected lifespan, pipe replacement and pipe rehabilitation have become major fields of engineering.

PW Trenchless Construction provides viable options such as pipe bursting, loose fit lining and internal pipe re-construction whether partial & fully circumferential. Learn more about pipe replacement & rehabilitation here!

More Info

Culvert Rehabilitation

The aging culverts under roads and highways in many case have reached the end of their engineered life-span. We consider the rehabilitation or replacement of these culverts to be vital to our built environment.

PW Trenchless has been a pioneer in working with MOTH, railway companies and municipalities in developing rehabilitation methodologies for the hundreds of thousands of culverts that currently exist in BC. We have offered solutions in both procurement and construction from design-build to sliplining, invert rehabilitation and full circumferential relining. Learn more about culvert rehabilitation here!

More Info

Point Repairs

Often pipe failure can be concentrated to one section, for various reason, leaving the rest of the pipe in good condition. The repair of these localized failures are know as external point repairs (EPR's).

EPR's demonstrate PW's ability to work as both a trenchless and civil contractor, completing EPR contracts using our civil contracting skills and assisting other pure trenchless contractors who only have the capacity to work in an existing pipe. Learn more about point repairs here!

More Info

Pipe Upsizing

Pipe upsizing is the fundamental concept of pipe bursting.

The vast majority of pipes are less than or equal to 200mm in diameter, but with today's densification practices of urban design, there is a major demand to increase current capacity to handle extra flow. Pipe bursting provides the ideal solution to this issue, particularly in an urban setting. Learn more about pipe upsizing here!

More Info

Horizontal Directional Drilling

Horizontal Directional Drilling is a low impact Trenchless construction service where pipe is installed in a shallow arc along a bore path which has been created by a drilling rig. Often the terms Horizontal Directional Drilling (HDD) and Directional Boring are used interchangeably, but in our industry we use the word “boring” when we utilize smaller sized drilling rigs with small diameters for short crossings in the hundreds of feet, and we use the word “drilling” when we utilize larger rigs with large diameters for long crossings in the thousands of feet. Learn more about horizontal directional drilling here!

More Info

Primus Lining

Primus Line® is a flexible sliplining solution for the trenchless rehabilitation of pressure pipes. The system consists of a flexible Kevlar® reinforced liner and specially developed end fittings. Primus Line® is not bonded to the host pipe and is self-supporting. An annulus remains between Primus Line® and the host pipe.

Developed by experienced engineers, the system is suitable for different media as well as various application needs and has already proven itself in numerous projects.Learn more about primus lining here!

More Info

Interested? Let’s Talk

  • This field is for validation purposes and should be left unchanged.

Clients We Serve

City of New Westminster logo
City of Delta logo
City of Surrey logo
City of Port Coquitlam logo
UBC logo
City of Coquitlam logo
City of Nanaimo logo
City of Pitt Meadows logo
City of Vancouver logo
BC Rail logo
City of Burnaby logo
City of Whistler logo
City of Victoria logo
City of Metro Vancouver logo
City of Squamish logo
City of West Vancouver logo
City of Richmond logo
City of Abbotsford
City of Chilliwack
Township of Esquimalt
City of Maple Ridge
City of North Vancouver
City of Port Moody
Regional District of North Okanagan
Town of Sidney
Ministry of Transportations and Infrastructure
District of Kent
Langley City
Township of Langley
White Rock

Join Our Team

When you join PWT, you become part of a community of people who are engaged in the most innovative practices in the Trenchless Industry. We have been instrumental in setting up a scientific method for cities to gain carbon offsets/credits from their use of trenchless construction. This system has been reviewed by the BC Government and has been approved as of December 2018. We expect to see it in common use shortly.

Stay At The Forefront Of Trenchless Technology

Subscribe to our newsletter for cutting-edge industry updates, expert knowledge, and exclusive content.

  • By clicking subscribe, you agree to receive emails from PW Trenchless and accept our Privacy Policy.

  • This field is for validation purposes and should be left unchanged.
Let's Talk